A specification matches project requirements to the offered configuration and acceptance evidence. Panel, motor and hardware documents retain their own scope and are distinct from a system declaration or test report. Record dimensions, usage and pending confirmations in the comparison table.

In a tender document, the technical specification defines product requirements and measurable acceptance criteria to make the bids comparable. A clause written without measurements (“quality panels shall be used”) is met differently in every bid, and at evaluation you are left with no comparable figure. A clause written with measurements both aligns the bids and becomes your acceptance criterion at delivery.

This article sets out how to build an industrial door specification, using the structure of our own product specifications. The reader in mind is the engineer preparing the tender, the technical buyer and the project office.

The preparation sequence

  1. Define clear dimensions, lift arrangement, usage and environment for each door.
  2. State the required function and performance to assess, with a relevant standard/class where applicable.
  3. Ask the bidder for model, configuration and the document/revision supporting each clause.
  4. Match evidence scope to the offered door; record missing evidence as an open question.
  5. Define in advance which documents and functional checks will be accepted at handover.

The dealer or project technical team prepares size and building information. Alkur does not conduct site surveys; product assessment follows the B2B partner channel.

How to verify document scope

A component test does not automatically prove complete-door performance. A feature requested in a specification is likewise not an achieved test result for the offered product. Review the manufacturer specification’s EN 13241-1 reference separately from the scope of each declaration, report or assessment submitted.

Information submittedWhat to check
Product specificationRequested feature and definition of the offered model
Performance/conformity declarationDeclarant, product scope and relevant configuration
Test reportSample, size, components and performance actually measured
Component documentThat component’s scope only; no automatic complete-door coverage

A document title alone is insufficient. Ask the bidder to clarify mismatched models, revisions or scope; do not relabel a report as a certificate or a specification as an independent test.

The eight headings of a specification

Specification clauses can be grouped under these eight headings. Each heading helps compare the proposed solution and the evidence supporting it:

  1. Document and scope requirements. Type of declaration or report, issuer, product/model scope and its match with the offered configuration.

  2. Panel characteristics. Infill density and type, panel thickness, sheet thickness, panel height options, surface pattern, standard RAL colour, performance classes.

  3. Tracks. Track size and wall thickness, the safe-stop arrangement at the top, the connection between the return tracks, compatibility with the lift types.

  4. Hinges and rollers. Material, noise behaviour, side capping profiles.

  5. Torsion springs. Standard conformity, cycle life and its alternatives, spring-break safety, corrosion protection.

  6. Cables. Construction (wire count and lay), tensile rating, cable-break safety.

  7. Sealing. Top, bottom and inter-panel seals, the perimeter seal and its flexibility at low temperature.

  8. Powered or manual operation. Manual opening during a power cut, the chain hoist option, pneumatic safety, locking arrangement.

How to write a measurable clause

Each technical clause should explain what will be assessed and how it will be accepted. Where a performance class is required, include its standard and scope. Size, equipment and document-delivery clauses do not all need the same formula.

Examples, from our own specification:

  • Panel: polyurethane infill at 40 kg/m³ between galvanised sheets, 40 mm panel thickness, 0.40 mm sheet thickness, panel height options of 460 / 500 / 560 / 610 mm.
  • Wind resistance: EN 12424 Class 3 (700 Pa, that is 0.700 kN/m² or approximately 71.4 kgf/m²). Writing “Class 3” alone is not enough; state the standard and the project pressure being specified.
  • Water tightness: EN 12425 Class 2. Air permeability: EN 12427.
  • Panel acoustic data: the manufacturer specification states R’w = 26 dB for the panel. This is not automatically an acoustic rating for the complete door system offered.
  • Torsion springs: conformity to DIN 17223, 15,000 cycles as standard life, with 25,000, 50,000 and 100,000 cycle alternatives available on request.
  • Cables: 6 × 19 = 114 wires laid around a polypropylene core, rated to 200 kg/mm²; cable-break safety as standard.
  • Seals: the perimeter and head seal shall retain flexibility down to −30 °C.

The 15,000- and 100,000-cycle options describe nominal cycle ratings for the selected spring assembly only. They do not establish a service life in years or a warranty for the complete door without considering daily use, door size, maintenance and other components. State the expected cycle load and the spring option in the specification.

State the size-dependent limits

Some options depend on dimensions, and leaving them out of the specification produces argument after the bid. A wicket door (840 × 1840 mm) applies to door widths of 5,000 mm and under; above that it is not applied and falls outside the warranty. Windows can be applied up to a width of 6,000 mm. Where the door width exceeds 5,100 mm, the panel joints require reinforcement profiles, support plates, double side hinges and long-shaft rollers.

Five mistakes that make bids incomparable

  1. Adding an unnecessary brand or model restriction. This narrows bids by name rather than by technical value. The applicable procurement rules and administrative specification must be checked separately; standards, classes and measurable performance should form the comparison baseline.

  2. Giving a class without its standard. “Class 3” on its own does not say which standard’s class it is; write EN 12424 Class 3.

  3. Leaving document scope unstated. If component documents are not distinguished from a complete-door declaration or report, the bids cannot be checked for equivalent coverage.

  4. Omitting cycle life. Bids given without a stated usage intensity cannot be compared; the same door gets priced against different spring classes.

  5. Leaving dimensions and lift type blank. Without the headroom, the lift type is assumed by whoever is bidding, and each bid prices a different installation.

Start from the ready specifications

Ready technical specifications for industrial sectional doors, high-speed PVC doors (roll and folding), dock levellers (hinged and telescopic) and dock shelters are on our Catalogues and Documents page, and the same files appear in the documents section of the relevant product pages. The TR and EN sections within a PDF can carry different revision dates. Before using either section in an export project, check the exact model, revision, technical scope and destination-market requirements.

Bid and acceptance matrix

RowInformation requiredWhat to record in the bid and at acceptance
GeometryOpening, lift and obstaclesConfirmed form/drawing and revision
PerformanceFunction or class needed for the projectModel-scoped declaration/report and pending confirmation
EquipmentPanel, spring, motor/controller and safetyIncluded models, limit type and accessory list
Operating profilePeak usage and expected movementDocumented component limits; uncertain calculations separate
HandoverDocuments and installed-function checksActual result, open finding and retest

Each requirement, offered response and supporting evidence appears side by side in the completed file. Two bids with different scopes are not compared as the same price item. Warranty and maintenance scope are confirmed separately in writing; spring cycles are not years or warranty duration.

Sources and evidence

Original sources for this publication and the specific information each link supports.

  1. BS EN 13241:2003+A2:2016, product standard and performance characteristics (opens in a new tab)
    Publisher:
    British Standards Institution
    URL
    knowledge.bsigroup.com
    Published:
    Last verified:

    Claim supported: Defines the product-standard scope for safety and performance characteristics of industrial, commercial and garage doors.

  2. BS EN 12424:2000, resistance to wind load classification (opens in a new tab)
    Publisher:
    British Standards Institution
    URL
    knowledge.bsigroup.com
    Published:
    Last verified:

    Claim supported: Identifies the standard under which a closed door's wind-load class should be specified.

  3. NORMTOR Industrial Sectional Door Technical Specification (opens in a new tab) PDF language: TR / EN
    Publisher:
    Alkur Kapı Sistemleri
    URL
    alkur.com.tr
    Last verified:

    Claim supported: Provides the manufacturer-document basis for the measurable panel, spring, cable, seal, wind and tightness clauses in this guide.

Record templates you can use

Templates are completed by the dealer and technical team; checks follow the device’s own manual.

Quote scope comparison worksheet

Compare the same need and configuration. Record included, excluded and unconfirmed items. Copy prices, warranty and timing from the offers. Empty fields do not indicate approval.

Show the blank record table
Quote scope comparison worksheet
Record field Requirement Offer A Offer B Confirmation needed
Offer date / reference / supplying dealer
Product family / model / quantity
Dimensions / measurement reference / drawing revision
Lift / platform / arm arrangement
Panel / curtain / infill and options
Motor / board / limit pairing
Supply / protection / wiring
Peak use / cycle requirement
Safety equipment
Access and activation equipment
Power-loss / manual-use arrangement
Document type / model scope / revision
Shipping / installation / responsibility scope
Warranty / maintenance / exclusions
Amount / currency / tax / payment / delivery terms

You can open the related FAQ question for a short answer.

Share this publication

Publications home

Contact

You're close to a journey full of innovation and inspiration

Reach our team for product selection, technical specifications or a price quote.

Alkur Kapı Sistemleri operates exclusively B2B. Sales and services are handled through dealers, distributors and business partners; we do not sell products or provide services or technical support directly to end users.

Our B2B sales and service model